Task

Deliverable

Weeks

Submitted

Due Date

  Project Execution Date

0

 

13-Jul-00

1

PROJECT WORK PLAN      

1.1

Draft Work Plan

6

5-Sep-00

24-Aug-00

1.2

Final Work Plan

12

 

5-Oct-00

2

FATE & TPORT OF P IN SOILS      

2.1

Initiate lab characterization

12

 

5-Oct-00

2.2

Begin construction

16

 

2-Nov-00

2.3

Complete lab characterization

24

 

28-Dec-00

2.4

Complete construction

28

 

25-Jan-01

3

EDUCATION OF LANDOWNERS      

3.1

Initial Workshop    

Oct-00

3.2

Final Workshop    

Jul-03

4

REPORTING ACTIVITIES      

4.1.1

Quarterly Report

36

 

22-Mar-01

4.1.2

Quarterly Report

49

 

21-Jun-01

4.1.3

Quarterly Report

62

 

20-Sep-01

4.1.4

Quarterly Report

88

 

21-Mar-02

4.1.5

Quarterly Report

101

 

20-Jun-02

4.1.6

Quarterly Report

114

 

19-Sep-02

4.2

Year 1 Annual Report

75

 

20-Dec-01

4.3

Year 2 Annual Report

127

 

19-Dec-02

4.4

Draft manuscript

150

 

29-May-03

4.5

Draft final report

150

 

29-May-03

4.6

All data, spreadsheets and programs

156

 

10-Jul-03

4.7

Final report

156

 

10-Jul-03

4.8

Final manuscript

156

 

10-Jul-03